The first batch of auctioned interstate transmission system (ISTS)-connected wind energy projects have been commissioned in India, for projects under Tranche I tendered by the Solar Energy Corporation of India (SECI) in November 2016. This comes after, Ostro Kutch Wind Private Limited successfully commissioned a partial capacity of 126 MW, for their projects in Bhuj, Gujarat.

SECI in February, 2017 conducted India’s first auction of wind power projects. The first of its kind auction garnered tariff of ₹3.46/unit, which was much lower than feed in tariffs in vogue those days. This was a 1 GW bid for projects to be connected on ISTS (Inter State Transmission System) wherein power generated from one state (renewable resource rich state) could be transmitted to other renewable deficient states.

Ostro, Mytrah, Green Infra and Inox Wind each one a project capacity worth 250 MW with their bids, Adani were awarded 50 MW of the project capacity. After conclusion of first-ever reverse auction for wind projects, power purchase agreements (PPAs) for wind projects aggregating 1,049.9 MW were signed between PTC India, a power trading solution provider, and developers who won bids to develop projects.

As a part of this bid, Ostro Kutch Wind was issued letter of award on April 5, 2017 for a capacity of 250 MW, with commissioning period of 18 months. A part capacity of 126 MW, located in Bhuj (Gujarat) was commissioned by Ostro on August 24, 2018, ahead of schedule. The energy generated from this project is being purchased by Bihar, Odisha, Jharkhand and Uttar Pradesh.

The first auction also signified a major shift from the earlier regime of state-specific Feed-in-Tariff (FiT) model to a Pan-India, market-driven mechanism. Beginning with this tender, the SECI has brought out five tenders for wind power projects of cumulative capacity of 7250 MW, of which 6050 MW capacity has been awarded. Besides SECI and NTPC being central agencies, the State agencies of Tamil Nadu, Maharashtra and Gujarat have brought out bids and awarded projects based on tendering.

According to MNRE, this 126 MW ISTS project marks the beginning of capacity additions in wind power based on market discovered tariffs, in line with the Government’s plan of having 175 GW renewable energy by 2022. Perhaps even the developers ould not have thought that tariffs would crash to as low as Rs 2.43 before stabilizing in the Rs 2.60 to Rs 2.75 range. It’s been a period of immense volatility since the first tender happened, with the industry still coming to terms with the new reality , some would say.

Ayush Verma

Ayush is a correspondent at iamrenew.com and writes on renewable energy and sustainability. As an engineering graduate trying to find his niche in the energy journalism segment, he also works as a staff writer for saurenergy.com.

Recent Posts

MoU FOR 25 CBG PLANTS : Indraprastha Gas Limited (IGL), CEID joint venture to add 125 TPD capacity

Indraprastha Gas Limited (IGL) has partnered with CEID Consultants and Engineering (CEID) to establish more…

48 minutes ago

Sistema.bio leadership meets NDDB to explore biogas expansion opportunities in rural areas

As India is charting new avenues to transform its waste into clean energy resources, the…

57 minutes ago

Tibet’s solar boom: Can China avoid repeating the mistakes of its bottled-water rush?

China’s renewable energy ambitions are reshaping the Tibetan Plateau, turning vast stretches of grassland into…

1 hour ago

All automakers to roll-out flex-fuel vehicles: Nitin Gadkari

Union Minister Nitin Gadkari has announced that Toyota’s flex-fuel Innova Hycross, capable of running entirely…

1 hour ago

REI Expo-2026 culminated in Rs 3,200 crore investment for India’s biogas sector: Indian Biogas Association (IBA)

India's biogas and compressed biogas (CBG) sector attracted investment pledges exceeding ₹3,200 crore at the…

1 hour ago

Egypt Wires Solar Plant Straight Into Aluminium Smelter; Indian Smelters Still Lean on Coal

Scatec has closed $217 million of development-bank debt for a 569 MW solar-and-battery plant that…

3 hours ago