Chinese Wind Installations Could be Halved in 2020: Coronavirus Outbreak

The coronavirus outbreak could lead to production delays in China’s wind turbine installations by up to 50 percent in 2020, according to research firm Wood Mackenzie. “We estimate production delays across the wind turbine supply chain will result in a 10 percent to 50 percent decrease in 2020 wind installations in China, compared to our Q4 2019 wind power outlook, which was at 28 gigawatts capacity,” said Xiaoyang Li, senior consultant, Wood Mackenzie.

She added that components without pre-existing bottlenecks, such as generators and converters, would be able to recover from first-quarter delays if the outbreak is brought under control in the next few months.

“In a best-case scenario, the epidemic is contained and production resumes by the end of March. In a bear-case, the epidemic could continue to impact the supply chain well into the middle of the year,” Li said.

According to the research agency, the outbreak has brought much of China’s wind turbine component production to a standstill in recent weeks. The quarantine and travel restriction measures will impact an already tight supply situation for key components.

It added that this could be bad news for wind markets such as China and the United States where developers are rushing to complete projects by end of the year to remain eligible for government subsidies.

The report further added that for non-China, Asia Pacific markets, the direct impact of the outbreak is minimal… these wind markets will need to lean on their domestic supply chains or imports from other low-cost regions such as India, Vietnam, and Southern Europe.

According to the analysis, 6 GW of installations targeting 2020 commercial operation day were identified as at-risk before the outbreak, requiring internal revenue service exemptions to maintain access to 100 percent value of the production tax credit, which is now likely to grow.

Recently, Indian rating and research agency CRISIL had reported that nearly 3 GW of solar projects, worth Rs 16,000 crore, could be at risk of penalties for missing their respective scheduled commercial operation date (SCOD) if the impact of Coronavirus on trade with China prolongs.

Source: saurenergy.com

I am Renew

Recent Posts

Modi Govt clears Rs 4,687 crore interest subsidy for ethanol making

The Central government has approved Rs 4,687 crore in interest subsidy support for ethanol projects…

2 days ago

Pharma company Nutraplus finalises CBG project site in South Gujarat

Mumbai based pharma company Nutraplus India Ltd has announced to have finalised a 3.5-acre leased…

2 days ago

Ethanol blending could save India Rs 38,000 cr annually: Suresh Gopi

India's Ethanol Blended Petrol (EBP) Programme could reduce the country's annual crude oil import bill…

2 days ago

BP profit surges; announces selling of $4bn US biogas business

Global energy conglomerate BP has announced plans to sell its USD 4 billion biogas business…

2 days ago

India’s Infistar Renewables, Finland’s Arciplug to make modular CBG plants in India

India’s Infistar Renewables has entered into a joint venture with Finland-based Arciplug Oy to manufacture…

3 days ago

Assam Cabinet clears CBG policy; other sustainability measures

The Assam Cabinet has approved the Assam Compressed Biogas (CBG) Policy, 2026, setting the stage…

3 days ago