Environment

Hydropower Construction: A Huge Risk for Himachal Pradesh

Highlighting the devastation and many risks which are associated with hydropower construction, especially in the ecologically fragile Himalayan regions like Himachal Pradesh, Himdhara Collective has released a report called ‘The Hidden Cost of Hydropower‘.

Himdhara Collective, an NGO based in Himachal Pradesh, for the last decade has been tracking and documenting the impacts of construction of for run-of-the-river (ROR) hydropower projects in the State which is the highest producer of hydropower in the country today making more than 10,500 MW electricity.

Himachal Pradesh has been a torchbearer for hydel power. It currently has 27 operational projects above 25 MW capacity each, totalling 9,755 MW. Eight more, totalling 1,855 MW, are under construction and 18 (5,218 MW) are in various stages of planning, Himdhara pointed out.

The report is a compilation of some primary and secondary pieces of evidence, of the impacts triggered by the construction of tunnels and other underground components for hydropower projects in the state. “The purpose of the document is to provide evidence to establish that there are severe risks and hazards associated with hydropower construction, especially in Himalayan regions like Himachal Pradesh,” says the report.

Damaged orchards at Urni village Pic Courtesy: Himdhara

[related_post]

The report highlights four major impacts of this kind of construction:

  • Geological impacts – triggering of landslides/slope failures leading to damage of roads, farms houses
  • Hydrogeological impacts – drying of springs and underground water sources
  • Muck Dumping – along rivers leading to increasing siltation, in forests and pastures
  • Safety negligence leading to accidents

The political class in Himachal and Uttarakhand have been batting for ROR projects for years. The report makes scathing remarks and blames “failure of policy, coupled with the absence of functional regulation and governance institutions“.

It blames the Central Water Commission and the Central Electricity Authority for overlooking “hazard vulnerability and safety aspects“. Despite being aware that geological challenges and surprises reportedly delay projects, the CEA “has not fed (this) into planning”.

The report pulled up the Expert Appraisal Committee of the Union Ministry of Environment, Forests and Climate Change for “hardly ever” deliberating on environmental hazards and disaster-vulnerability of such projects. Little heed is paid even when issues are repeatedly raised by environmental researchers, activists and community representatives, the report alleged.

The report adds that this has been despite CAG Audit Report revealed that of 196 projects studied, 32 % of the cases had procedural violations in following the norms for environmental impact assessment (EIA) studies.

It blamed the state Pollution Control Board for not monitoring violations. Unless a central law makes states responsible for the safety of dams, authorities and regulation will continue to be weak, it added.

On top of that, about 40 hydel projects were decided to be bailed out of bad loans worth Rs 16,000 crore in 2016-17. It was an opportunity to review policy and viability. A report by the Parliamentary Standing Committee on Energy, tabled in 2018, however “fails to look into the challenges faced by this sector,” according to the report. While only projects up to 25 MW capacity were considered eligible for financial assistance and loans at lower interest rates, the committee proposed to recognize projects with a capacity above 25 MW as renewable sources.

The report echoes with various studies and reports that have been trying to educate governments and authorities about the dangers of large hydro electric projects. While the country is moving ahead with other sources of Renewable energy like solar and wind, huge constructions like that of dams should be now avoided. The cost of these mega structures are usually borne by affected people or are transferred to the public exchequer, in cases of unwelcome surprises. Costs that producers have been forced to bear have led to financial losses, bad loans and cumulatively a slump in many Himalayan states too.

To read more click here

I am Renew

Recent Posts

Farm Waste To Power India’s SAF Moment

India has committed to reaching net-zero emissions by 2070, and aviation, one of the fastest-growing…

2 days ago

Punjab’s 90% Drop in Farm Fires May Be a Trick of the Satellite’s Clock

Every winter for the past several years, Punjab's government has pointed to one number: farm…

3 days ago

Delhi’s Winter Pollution Plan Goes Permanent — Here’s What Changes From November 1

Delhi's winter pollution problem has a new answer: a plan that doesn't need to be…

4 days ago

IFAT India 2026 advances technology and partnerships for India’s water and waste infrastructure

IFAT India 2026 concluded at the Bombay Exhibition Centre in Mumbai after bringing together 20,118…

4 days ago

UltraTech Powers First Integrated Unit With 100% Green Energy

Indian cement company UltraTech Cement Limited has enabled its integrated cement manufacturing unit, Kukurdih Cement…

5 days ago

India’s SAF Mandate Gains Momentum; Global Industry to Gather at 2nd India SAF Conclave & Awards 2026

Following the Government of India's recent indication that the country's Sustainable Aviation Fuel (SAF) mandate…

1 week ago