Sustainability

As Kakrapar’s Unit 3 Goes Live, India’s Nuclear Dreams In Focus

In 2019, the Department of  Atomic Energy, which runs India’s 22 nuclear power reactors  through the Nuclear Power Corporation of India, announced plans to establish  21 new nuclear power reactors .  These were to include 10 indigenously designed Pressurised Heavy Water Reactors (PHWRs) – with a combined generating capacity of 15,700 MWe into operation by 2031. That would take total India’s nuclear generating capcity to over 22,500 MWe by 2031.

The Kakrapar success is notable not just for the use of Indian technology and domestic vendors like L&T that executed the project, but also the continued success of the country’s focus on PHWR driven expansion of its nuclear power capacity. In fact, starting this year, the country hopes to commission a reactor every year for the next seven years, before the remaining reactors come online more quickly. Almost all the new reactors are planned for the 700 MWe configuration.

However, in the larger scheme of things, while the addition to the nuclear capacity is very useful from a carbon emissions   target perspective by 2030 and beyond, the fact remains that the time taken for each nuclear power reactor to be finished is probably the biggest reason why hopes are not very high for nuclear power to increase its share of the total power mix in India from the current 2 percent.

It was back in April 2007 that  the government first approved plans for the first four of the eight planned 700 MWe PHWR units, with KAPP 3 the first of many.  Kakrapar units 3 and 4 in Gujarat  and Rajasthan units 7 and 8, to be built by Hindustan Construction using indigenous technology. Construction approvals followed by 2009.

Basic site works at Kakrapar were completed by August 2010. First concrete for Kakrapar 3 and 4 was in November 2010 and March 2011 respectively, after Atomic Energy Regulatory Board (AERB) approval. The AERB approved Rajasthan 7 and 8 in August 2010, and site works then began. First concrete for those units was in July 2011. Construction had been expected to take 66 months, but dragged on well beyond, as we can see. This is not an issue unique to India, and has been cited as a key reason for the issues with nuclear to be taken seriously.  Of course, with both Russian and Chinese state backed firms pushing the tech yet, more and more countries are willing to consider it, due to the financial support that follows.

For India, despite the compete involvement of the government in the form of the Department of Energy and Nuclear Power corporation, it has been difficult to accelerate approvals and construction, due to multiple issues.  The use of the PHWR technologyis expected to reduce a lot of local resistance, thanks to the extra safety features the new technology adds now.

The key of course is the use of thin walled pressure tubes instead of the large pressure vessels that are used in pressure vessel type reactors. This results in the distribution of pressure boundaries to a large number of small-diameter pressure tubes, lowering the potential damage  from an accidental rupture of the pressure boundary.

Now, there is also a dedicated ‘Passive Decay Heat Removal System’, which can remove decay heat  from the reactor core on its own. This is a feature that was added after the Fukushima disaster in Japan, which dealt a huge blow to nuclear power worldwide by ratcheting up fears of a similar accident in plants elsewhere.

Interestingly, unlike thermal power, nuclear power  ,at a probably long term cost of RS 2.80 to Rs 2.85, remains competitive with solar , giving some hope that the push for more nuclear, at the expense of coal, will possibly continue. Especially if the next big hope for domestic technology, a 900 MWe reactor, can be realised over the next three years.

 

I am Renew

Recent Posts

BELIEVE IT OR NOT: Govt of India has ‘NO FUNDS’ for study of ozone pollution in Delhi

The government’s grand claims of ‘Transforming India’ sometimes turn out to be just ‘creative writing.’…

3 hours ago

TruAlt Bioenergy targets expansion in ethanol-CBG-SAF

Bengaluru based TruAlt Bioenergy Ltd has convened its fifth annual general meeting (AGM) and its…

3 hours ago

Odisha Minister blames ethanol for sugar price rise

Krushna Chandra Patra, Minister for Odisha Food Supplies and Consumer Welfare department has linked the…

3 hours ago

Delhi reclaims ‘100 Acres’ from legacy waste at major landfill sites

Delhi Chief Minister Rekha Gupta has informed that around 100 acres of land have been…

1 day ago

GOA: Chief Minister inaugurates ‘Integrated Waste Recycling Facility’ operated by PureCycle Recycling

An integrated waste recycling facility with an annual processing capacity of 50,000 metric tonnes has…

1 day ago

Himachal Pradesh says no to new ethanol plants over water, pollution concerns

The controversy concerning the Ethanol Blending Program in the country has multiple nuances. Now, the…

1 day ago