Adani (ATGL) seeks bids to build CBG plant of 500 TPD in Ahmedabad

Adani Total Gas Limited (ATGL) has sought proposals from EPC Contractors interested in participating in the procurement process for “Design, Engineer, Build, and Operate 500 TPD Capacity Bio- CNG (CBG) Plant for Treatment of Source Segregated/ Mixed Organic Fraction of Municipal Solid Waste at Ahmedabad, Gujarat.

The last day of submitting the bids is June 24, 2024. The pre-bid meeting is on June 6 and the notification of ATGL says that all prospective bidders are required to visit the site in person at their own expense prior to participating in the Pre-bidding process. One joint visit will be coordinated by ATGL on 22- 05-2024.

The location of the proposed CBG project is Pirana, Gyaspur, in Ahmedabad of Gujarat. The total area of the CBG project is 17 acres and the selected contractor will be required to build the CBG plant for the production of compressed biogas, solid organic manure and liquid organic manure. The production of briquettes has been kept as optional.

The contractor will have to build the CBG plant within 12 months (one year).

Within the CBG plant project, the contractor will need to build the following important installations: Municipal Solid waste Dry Pretreatment, Wet Pretreatment, Hydrolysis tanks, Digesters, Buffer tanks, BioGas purification system, EOT crane, Biogas flaring system, Gas storage balloon, Compressor, Storage Cascades, CO2 liquefaction plant, Solid liquid separator, ETP, Fertilizer processing & packaging plant, Laboratory, Office, Control room, SCADA etc.

Adani Total Gas Limited (ATGL) is a prominent Private and Listed City Gas Distribution (CGD) entity in India with over 15 years of experience in the development, operation, and maintenance of City Gas Distribution Networks.

In line with its commitment to supporting the India’s vision of “Swachh Bharat”, Adani Total Gas Limited (ATGL) has established Adani TotalEnergies Biomass Limited (ATBL) as a wholly owned subsidiary dedicated to setting up and operating Biogas plants utilizing Agricultural Waste and Municipal Solid Waste.

Subhash Yadav

Recent Posts

Prime Minister to lay foundation stone of GAIL’s 300-TPD CBG project in Bengaluru

Government owned Gas Authority of India Limited (GAIL) has proposed to set up a 300-tonne-per-day…

4 days ago

International Energy Agency (IEA) finds India’s CBG plants running at mere 35% capacity

The International Energy Agency (IEA) has revealed that India’s compressed biogas (CBG) plants are operating…

4 days ago

Bunge, GDM make joint venture for oilseeds based low-carbon fuel feedstocks

Bunge, a premier agribusiness company that connects farmers to food, feed and fuel markets, and…

5 days ago

Uttar Pradesh mulls new 78-biogas projects across state

The state government of Uttar Pradesh is planning to develop a network of biogas plants…

5 days ago

Ghazipur ‘Waste-to-Energy’ Project: Centre approves Rs 122 crore for viability gap funding

The Central Government has approved Rs 122 crore in financial assistance for the proposed 2,000-…

5 days ago

Central Govt rejects Karnataka claims of excess ethanol blending in petrol

The Ministry of Petroleum and Natural Gas has rejected claims by the Karnataka Government regarding…

6 days ago