UP Regulator Orders Compensation To Consumers For August 12 Disconnections

The August 12 disconnections in Uttar Pradesh which affected  1,58,000 houses with ‘smart’ meters  is finally a little closer to closure. The state regulator, Uttar Pradesh Electricity Regulatory Commission (UPERC)As it turned out, this was no ordinary outage, being a remotely activated ‘disconnection’ actually, caused by mismanagement at the distributor end. The cut placed the smart meters installed in all the houses firmly in the spotlight.

While power was restored gradually over the day, the damage the incident did to perception around smart meters and their management was significant. That is one reason the Uttar Pradesh Electricity  Regulatory Commission (UPERC),  in suo moto proceedings it initiaied on the matter, had sent notices to the states key power entities, which includes the UPPCL, the  state’s four discoms, and  the Kanpur distributor .

Not surprisingly perhaps, the response was poor, with  almost all the respondents passing on the buck, blaming other parties contracted for the fiasco. Incredibly, in their defense, the discoms claimed protection since there is no provision in the statutory and regulatory framework for UP for cases involving smart meters. Specifically for UPPCL, the regulator took umbrage to the fact that the notice sent to the managing director was not even responded to directly, with the Director in the firm finally responding.

The UPERC bench, after going through the responses,  pointed out that the response from UPPCL and the others  showed “total apathy and grave callousness” to the regulatory directions. ” It is time that the senior management owned up to their responsibility, instead of abdicating it to their vendors/suppliers/private parties”, it added.

Taking exception to the the terming the disconnections as a ‘disruption in supply’ the bench said it was a a clear attempt to brush off responsibility. The commission also blamed the UPPCL for the breach of data privacy, against its instructions, that the disconnections had shown up.

Raj Pratap Singh, Chairman, UPERC

Pointing out that the most basic requirements of law, like a 15 day notice period before any disconnection, offer enough reason to pull up the discoms, the UPERC bench went on to propose a compensation of Rs 100 per consumer  with a further Rs 50 per day for delays beyond a day. The respondents were given till Sep 3 to show cause against this , if at all. The discoms had claimed that almost 94 percent of the connections  had been restored in the first 6 hours.

Incidentally, the director of Energy Efficiency Services Limited (EESL), Venkatesh Dwivedi, had tweeted days later to say that  the state heads of EESL and L&T had been placed under suspension for dereliction of duty. EESL has  been spearheading the smart meter push across the country.In all the cases, the smart meters started displaying ‘disconnection due to non-payment of monthly arrears’ as the reason for the power snapping off.

Smart Meters  promise to significantly improve the discoms’ billing efficiency and reduce losses. UP’s  MoU with EESL envisages replacement of 40 lakh conventional metres with smart meters and as many as 10 lakh smart meters have already been installed.

 

 

 

Prasanna Singh

Prasanna Singh is the founder at IamRenew

Recent Posts

BPCL commissions 2G ethanol project in Bargarh

Bharat Petroleum Corporation Limited (BPCL) has commissioned a cutting-edge second-generation (2G) bioethanol refinery in Bargarh,…

21 hours ago

GUJARAT: 10 bio-CNG plants to power Anand villages to beat LPG shortages

In response to restrictions on commercial LPG cylinders, villages in Gujarat’s Anand district are embracing…

21 hours ago

IBA recommends 20% CBG blending for clean mobility in Delhi

The Indian Biogas Association (IBA) has recommended that the Delhi Government consider blending up to…

21 hours ago

Solar could meet ASEAN’s new power needs at half the cost of gas: Ember study

Global energy think tank Ember has revealed in its new analysis that replacing ASEAN’s planned…

1 day ago

WOTR rejuvenates 147 water structures in rural Rajasthan

The Watershed Organisation Trust (WOTR) has announced to have marked a significant milestone by rejuvenating…

1 day ago

BPCL, Sembcorp joint venture gets 10KTPA green hydrogen contract from Numaligarh Refinery

Bharat Petroleum Corporation Limited (BPCL), a Fortune Global 500 company and a Maharatna PSU, has…

1 day ago