Will 2 Paise/unit produced help state governments roll out a welcome for renewables?

The latest news of the central government  introducing a financial incentive for states when it comes to renewable energy production hopes to tackle two key issues facing developers. land and distribution access for their power produced. Henceforth, for every unit of renewable power produced in a state, the state will get 0.02 rupees or 2 paise, as incentive, as mentioned in a letter addressed to all principal secretaries of states, besides the government’s own key nodal agency, SECI and developers.

The 2 paise incentive, assuming production of 1.5 million units annually on a 1 MW installation, works out to Rs 30,000 per MW, or Rs 3 crores for every 1000 MW. At a typical efficiency or CUF of between 17 to 20%. It might not look like a lot of money, but, when weighed from a perspective of largely unutilised land that i sought to be used for solar, perhaps, not a bad move.

For states with aggressive solar plans especially in North India, be it Rajasthan, MP or even UP, the incentive should certainly help. Considering the poor response across the country to discoms too, maybe there will be a case to incentivise state discoms too to support rooftop solar by getting a similar or higher incentive.

Wind Power producers have been particularly hard hit in Gujarat, where the state government’s new land policy has placed all previous projects in limbo, forcing SECI to extend the deadlines for most. Tranche 1 to 6 of the auctions have been particularly badly hit, and in at least a few cases, might eventually lead to cancellations too.

Two mid sized developers we spoke to expressed ignorance of this latest directive, and had their doubts about its effectiveness. In their view, even though developers might be able to load this cost on their upcoming bids, the low bids of 2017-18 have already strained the financials of most, and the delays have done enough damage to hurt growth for some time to come.

For consumers, the struggles to get states to move faster are bad news, as not only does it delay India’s renewables march, it also increases power costs eventually.

Published with permission from Saurenergy.com

Prasanna Singh

Prasanna Singh is the founder at IamRenew

Recent Posts

Andhra Pradesh to build 5 new CBG plants in urban areas

The state government of Andhra Pradesh has approved an outlay of nearly Rs 60 crore…

2 days ago

Sanjivani Cooperative develops 12 tonnes bio-CNG project employing sugar waste

The multi-state cooperative society - Sanjivani Cooperative Sugar Factory - has strengthened its clean energy…

2 days ago

India to start carbon market trading within 4-months

India is set to launch formal trading in its domestic carbon market within the next…

2 days ago

GAIL India makes strategic investment in TruAlt firm for CBG projects

GAIL (India) Ltd has invested Rs 13.54 crore in Leafiniti Bioenergy, a subsidiary of TruAlt…

2 days ago

CBG–CGD Synchronisation Scheme extended till 2047

The central government has extended the Compressed Biogas (CBG)–City Gas Distribution (CGD) Synchronisation Scheme until…

2 days ago

DHL, Malaysia Aviation Group come together to bolster SAF

Global logistic conglomerate DHL Express has announced to have signed an agreement with Malaysia Aviation…

2 days ago