Report From India’s Central Electricity Authority Indicates Tough Time For Renewables

A report released by India’s Central Electricity Authority (CEA) on August 21, indicates some huge issues for the ‘pipeline’ of solar (and wind) projects. Looking at the delays and reasons for these delays in many cases, and the evolving situation on the ground,it becomes amply clear that the 2022 target of 175 GW is at least a miracle away, especially in its original version without large hydro being counted in.

The report, a developer and project wise compendium of the situation as per data collected by the CEA, has a detailed project wise breakup  with physical progress, attributes and reasons for delays. A total of 39.4 GW projects seems to be stuck/delayed, and going by the reasons cited, ranging from  Covid, transmission issues, absence of PPA/PSA, land acquisition issues, financial closures, in fact pretty much the full checklist of the most vital pre-requisites, you know that this list is not going to get shorter anytime soon. The worst part of the report? It covers only utility scale solar and wind, where India was supposed to have actually progressed well. Rooftop solar and its complete failure to take off is off course not even worth documenting right now.

If you thought certain developers have it better, then you will be surprised. While the travails of developers like ACME Solar have been well documented, practically  every single large developer that has won a project in the past 3 years is in the list. While some like ACME and  renew Power have even tried to cancel some of the most delayed projects citing force majeure, many other projects in the list will meet those conditions in the coming months.

Keep in mind that the slump in power demand, a corollary of the Covid pandemic, is not helping matters at all. Key states like Tamil Nadu and Karnataka have declared a formal go slow on new renewable additions, while many others have their own special issues, from Andhra Pradesh with its wholesale demand for renegotiation of PPA’s (Power Purchase Agreements) to Punjab with a flat demand for a discount.  States like those in East India, already behind on the renewable curve,  have almost no reason to try and catch up, considering the state of power demand, and worse the state of their discoms.

For the record, in the report, 61 solar projects have been listed, with a total capacity of 20.1 GW, where an extension seems to have been granted due to the Covid 19 outbreak. This will be a 5 month extension, as per the MNRE order earlier, though in at least 30 percent of these projects, 5 months will definitely not cut it, looking at the progress made, be it financial closure, land acquisition, material ordering or transmission availability.

A further 8 large Solar projects, mostly under SECI, have yet to achieve basic PPA/PSA signing. Readers will know that for SECI projects, a PPA between SECI and the developer is usually a back to back arrangement along with the PSA (Power Sales Agreement) between SECI and a state discom or any other purchasing entity. With state discoms going slow, SECI is in no position to execute the promised PPA’s.

The situation is even worse in wind projects, which has been apparent for some time now. 11 GW of projects are struggling, of which 1.4 GW of projects involve developers  requesting cancellation, already covered by us. For the rest, every project has an issue with land acquisition, again an issue that has been highlighted for over 12 months now, with no apparent progress,as it turns out.

The report is a reality check for industry watchers, and will be a sobering read for the relevant people at the MNRE  too, where a concerted effort has been made to talk up the prospects of the sector. Unfortunately, actual action on the ground has simply not been enough to prevent a slide that is making hopes of  100 GW of solar by 2022 look simply improbable now. The biggest stumbling block, even with the best efforts, including the proposed amendments in the Electricity Act, is the demand slump, and the financial state of the discoms in most states now. Consider the fact that the 90,000 core funding scheme launched to support discoms is already looking inadequate, barely two months since it was launched, with discom outstandings owed to generation firms climbing to almost 1,40,000 crores in the period.

Clearly, the politically easy ways to manage the crisis are  long over. It remains to be seen just what will be sacrificed in the coming months, to bring a semblance of reality to reality versus the intent declared by the MNRE for the past few months.

By Arrangement With SaurEnergy

Prasanna Singh

Prasanna Singh is the founder at IamRenew

Recent Posts

Kirloskar Pneumatic unveils ‘Tonalli’ waste-to-biogas solution

Kirloskar Pneumatic has unveiled ‘Tonalli,’ a decentralized waste-to-energy solution designed to convert organic waste into…

6 days ago

Emrock Corporation clears Rs 33-crore bio-CNG project

Ahmedabad-based infrastructure and construction company Emrock Corporation has said that its subsidiary, Emrock Energy Pvt…

6 days ago

India notifies new standards for 30% ethanol blending in petrol

Amid rising global energy concerns, the Union government has introduced new fuel standards permitting ethanol…

6 days ago

Anaergia gets C$58 million order from Neogenyx Fuels

Anaergia Inc, through its subsidiary Anaergia Technologies, has entered into a C$58 million contract with…

6 days ago

WEST ASIA: Priya Blue Group joins ASRY to build largest ship recycling in Bahrain

Priya Blue Group, one of South Asia’s leading environmentally responsible ship recyclers, has partnered with…

6 days ago

Bhutan begins construction of 25-MW Begana hydropower

Bhutan has officially begun construction of the 25-megawatt Begana Integrated Multipurpose Small Hydropower Project, marking…

6 days ago