Land Approval Delays in Karnataka has the MNRE Concerned

Barely a day after news reports announced its elevation to the no. 1 ranking for renewable energy in India, Karnataka faces an unexpected complaint. Slow progress on and allotments for solar projects. The Ministry of New and Renewable Energy (MNRE) has written to the Karnataka government citing 24 solar power projects with total capacity of 970 MW being implemented by the Solar Energy Corporation of India (SECI) under MNRE’s 2,000 MW Viability Gap Funding (VGF) program in Karnataka, and expressing its concern over delays in granting land approval for these various solar projects.

The ministry believes this delay in land approvals by the Karnataka state government is capable of affecting the country’s renewable growth trajectory. Delays on part of the Karnataka government has led to two problems, one in the form of financial stress to the developers who’ve had their expensive projects stalled but also a negative sentiment for the sector that might affect the development of solar power industry. For the record, Karnataka added almost 5 GW of renewables capacity in 2017-18, mostly solar.

According to guidelines and bidding conditions of the VGF program, the winning bidder needs to submit the financial closure of the project with all the necessary documents within seven months of the signing of the PPA (Power Purchase Agreement). One of the necessary documents for financial closure needs to be the papers citing the land approval for the project. Due to which, the SECI now have multiple projects delayed because their land approvals are still pending.

The letter, signed by Anand Kumar, the secretary at MNRE, has asked the Karnataka government to give adequate direction to the concerned departments.

A key reason for the vast interest of the central ministry in the delay of the projects comes from the fact that Karnataka is the leading solar state now. In the first three months alone of this year, the state matched its annual record of 2 GW of installations. With its showcase state stumbling, perhaps it is natural for MNRE to be more worried and act with alacrity.

copyright:iamrenew.com

Ayush Verma

Recent Posts

India’s Infistar Renewables, Finland’s Arciplug to make modular CBG plants in India

India’s Infistar Renewables has entered into a joint venture with Finland-based Arciplug Oy to manufacture…

1 day ago

Assam Cabinet clears CBG policy; other sustainability measures

The Assam Cabinet has approved the Assam Compressed Biogas (CBG) Policy, 2026, setting the stage…

1 day ago

Tamil Nadu to bring battery storage & recycling policy

Tamil Nadu is set to introduce a dedicated policy for Battery Energy Storage Systems (BESS)…

1 day ago

As “Day Zero” Warnings Persist, India’s Cities Still Aren’t Catching the Rain They Get

Down To Earth's August 1–15 print edition leads with a factsheet on a problem this…

2 days ago

IOCL agrees to build two CBG plants in Delhi

The Municipal Corporation of Delhi (MCD) has signed a Memorandum of Understanding (MoU) with Indian…

2 days ago

India’s ethanol programme being fuelled by rice & maize

Rice and maize have become the dominant feedstocks for ethanol production in India, with maize…

2 days ago